Most of the work happens before you open the kit. This guide walks through the full sequence and the numbers that matter. Times and limits come from Sika's published Sikafloor-200 garage kit instructions, used here as a worked example. The sheet for your own kit takes priority.
Direct Answer
The short answer
Test the slab for moisture, then degrease it, grind it to a fine-sandpaper texture, and repair the cracks. Mix one kit at a time, brush the edges, roll on the first coat, and recoat within the label's window. Plan on about four days of work, then about three more before you park on it.
Takeaways
Run the moisture test first. A damp slab can make the rest of the work a waste.
Oil has to come off before you grind, or the grinder spreads it across the floor.
At 68°F this kit gives you 8 to 24 hours to recoat. Missing that means sanding.
Cooler garages add days. At 50°F full cure takes 10 days instead of 7.
What you need
Sika lists these supplies for its kit. Add degreaser, crack filler, painter's tape, and a stopwatch or phone timer.
Epoxy kits, resin and hardener. See the table below for the count.
Moisture meter or an 18 × 18 in plastic sheet and duct tape.
Thermometer for the slab and the air.
Floor grinder or sander, plus a vacuum. Rental usually runs $100 to $200 a day.
Mixing drill with a paddle. Sika says not to mix by hand with a stir stick.
Paint brush for the edges and a 5 mm lint-free roller with an extension pole.
Mask, gloves, and safety glasses. Check the safety sheet for your kit, since some products call for a respirator.
How many kits for your garage?
Kit counts depend on the coverage printed on your label. This table uses 200 sq ft per kit per coat, 2 coats, and 10% extra. For a 400 sq ft garage that is 400 × 2 × 1.1 ÷ 200 = 4.4, so buy 5 kits. Enter your own label coverage in the epoxy floor coverage calculator.
Garage
Area
Kits for 2 coats
1-car (12 × 24 ft)
288 sq ft
4 kits
2-car (20 × 20 ft)
400 sq ft
5 kits
2-car (24 × 24 ft)
576 sq ft
7 kits
3-car (24 × 36 ft)
864 sq ft
10 kits
Rough or porous concrete soaks up more on the first coat. For a flake floor, add the chips with the epoxy flake calculator.
Sample timeline at 68°F
Day
Work
Why it takes this long
Day 1
Empty the garage, degrease, tape down the moisture test
The plastic sheet needs at least 24 hours
Day 2
Check the test, grind, repair cracks
Filler has to cure before you sand it flush
Day 3
Vacuum, coat the edges, roll the first coat
Start when the slab is cool and shaded
Day 4
Roll the second coat
Recoat 8 to 24 hours after the first coat
Day 5
Walk on it
24 hours after the last coat
Day 7
Light vehicles
72 hours after the last coat
Day 11
Full chemical resistance
7 days after the last coat
Based on the Sikafloor-200 kit at 68°F. A damp slab or a failed test stops the schedule at Day 2.
Step 1: Check the slab and the weather
Slab age: Sika prefers a new slab to cure for at least 90 days before coating.
Moisture: tape an 18 × 18 in plastic sheet to the concrete and wait at least 24 hours. Condensation or darker concrete means it is too wet to coat. A meter reading should be 4% or less for this kit.
Weather: stay between 50°F and 86°F with humidity no higher than 80%. Outside that range you risk wet spots and poor adhesion.
Old coatings: test adhesion and compatibility first. Anything loose has to come off, and the rest needs sanding until no gloss remains.
A slab that fails has to be solved before you buy a kit. The basement epoxy floor cost guide covers moisture testing and vapor barriers in more depth.
Step 2: Clean and degrease
Sweep and vacuum, then treat every oil and grease stain with a concrete degreaser. Do this before you grind, because sanding spreads the oil across the floor. Oil left in the concrete causes poor adhesion, black spots, and wet, uncured patches. If you rinse with water, let the slab dry fully before moving on.
Step 3: Grind the concrete
The surface needs an open profile. Sika specifies ICRI CSP 3, which feels like fine sandpaper, and warns that smooth concrete can lead to peeling later. Its kit calls for mechanical prep with a sander or grinder, which you can usually rent.
Some budget kits allow acid etching instead. Follow your label, but grinding gives a more reliable surface and removes old sealers that acid will not.
Drop water on the ground slab. If it beads, a sealer or smooth patch is still there.
Pay attention to the edges, since a floor grinder will not reach them. Use a hand grinder or sander.
Wear a dust-rated mask and use a vacuum shroud. Concrete dust is harmful to breathe.
Step 4: Repair cracks and holes
Fill cracks and holes with a crack filler made for concrete. Once it has cured, sand it level with the slab, then sweep and vacuum everything again. Any dust left behind ends up in the coating. A crack that keeps moving will likely show through later, so expect some repairs to be cosmetic.
Step 5: Plan your batches
Mix only once the prep is finished and the moisture result is acceptable.
Split the floor into sections, one per kit, and mark them with tape or chalk at the walls. This keeps each kit spread to the right thickness.
Never mix two kits at once. Sika warns that the working time is limited.
Coat as the day cools and out of direct sun. Sika warns that rising temperature makes concrete off-gas, which causes bubbles and pinholes.
Tape the line at the garage door if the slab runs past it, and pull the tape after about 45 minutes, before the coating sets.
Plan your exit. Start in the far corner and finish at the door.
Step 6: Mix the resin and hardener
Stir each part on its own first so it is uniform. Add the hardener to the resin at the ratio on your label, then mix with a drill and paddle for the time the label gives. Start coating right away. Mixed epoxy heats up faster in a pail than on the floor: Sika's kit starts to gel after 30 minutes in the pail, against about 45 minutes of working time on the floor at 77°F.
Step 7: Brush the edges and roll the first coat
Brush a band of coating along the walls in the far corner.
Pour a 1 to 2 in wide ribbon along the back of the section.
Spread it with the roller to the label thickness. This kit targets 8 mils, or about 200 sq ft per kit.
Back-roll with light pressure to remove puddles, ridges, and roller marks.
Keep a wet edge. If the next batch comes too late, the overlap can show in the finished floor.
Check your spread rate as you go. Our epoxy floor thickness guide shows how to convert wet film to dry film.
Step 8: Add flake, if you want it
Flake goes into the wet coat, so have it ready before you start rolling. Throw it upward and let it fall evenly. A full broadcast keeps going until the wet coat cannot hold any more. A partial broadcast leaves the base color showing. A full broadcast needs scraping smooth once cured, and a clear topcoat over the chips. Use the epoxy flake calculator to work out the pounds and boxes.
Step 9: Apply the second coat in the window
Roll the second coat the same way, inside the recoat window on your label. If you miss it, the surface has to be sanded until the gloss is gone and vacuumed clean before you continue. Temperature moves the window, as this table from Sika's sheet shows.
Slab temperature
Recoat (min / max)
Foot traffic
Light vehicles
Full cure
50°F
16 / 48 hours
30 hours
5 days
10 days
68°F
8 / 24 hours
24 hours
3 days
7 days
86°F
6 / 24 hours
16 hours
2 days
5 days
Sikafloor-200 Garage Epoxy Kit. Measure the slab, not just the air. Concrete stays cold well after the air warms up.
Step 10: Let it cure
Keep water, damp, and condensation off the floor for at least 72 hours, or it can show white stains or lose its gloss.
Do not drive on it early. Give it the full vehicle time on your label, and longer in a cold garage.
Wait for the full cure before you clean with chemicals or leave oil spills on it.
Clean tools straight away with the solvent your sheet names. Cured epoxy can only be removed mechanically.
Should you do it yourself?
Materials for a 400 sq ft garage run about $200 – $1,080. A professional epoxy floor runs $1,600 – $4,000, and most of that labor goes into prep. Bob Vila's advice is that applying epoxy is the easy part and preparing the floor is the hard part.
Do it yourself if the slab is dry, sound, and uncoated, and you can keep the garage empty for about a week.
Hire a pro if the slab fails a moisture test, has an old coating, or needs major repairs. Check a quote against the epoxy garage floor cost calculator.
Steps, limits, and timing follow Sika's instruction sheet for one DIY kit, used as a worked example. We publish planning tools and have not tested this product. Other kits differ, sometimes a lot, so follow your own product's instructions and safety sheet.
Quick kit and gallon numbers for the most common garage size.
Open page
FAQ
Questions people ask before buying epoxy
How long does it take to epoxy a garage floor?
Plan on about four days of work: a day for cleaning and the moisture test, a day for grinding and repairs, and two days of coating. At 68°F, add three days before light vehicles and seven before full cure.
Do you have to grind concrete before epoxy?
Sika's kit requires mechanical prep to a CSP 3 profile. Some budget kits allow acid etching. Grinding is the safer choice, and it is the only way to remove an old sealer or a thin coating.
How cold is too cold to epoxy a garage floor?
Sika's kit stops at 50°F, and Concrete Network says epoxy should not go down below that. Check the slab temperature with a thermometer, because concrete can be colder than the air.
How long before you can drive on an epoxy floor?
Sika's kit needs a minimum of 72 hours at 68°F, or 5 days at 50°F. Other products differ, so use the vehicle time on your label.
Can you epoxy over a painted or coated garage floor?
Only if the old coating is firmly bonded and compatible. Sand the whole surface until the gloss is gone, vacuum, and test a small area. If it peels, remove it first.
Do you need a primer?
It depends on the system. Sika's kit goes straight onto prepared concrete, while many professional systems start with a primer. A moisture-tolerant primer is a separate product for damp slabs.
How much epoxy a garage or basement floor needs: turn square feet, coats, and your kit's coverage rate into gallons and kits to buy, with waste and material cost.
How many pounds of flake for an epoxy floor: about 12.5 lb per 100 sq ft for a full broadcast of 1/4 in chips. Full or partial broadcast, flake size, and boxes to buy.
The real pros and cons of epoxy flooring: how long it lasts, why it peels or yellows, what it costs per year, and when another floor is the better choice.